Table 2 Wedge 1.2—on-site electricity production with photovoltaic field: assumptions.

From: From the “Green Station” to the “Blue Station”: the role of the renovation of railway stations in the ecological transition of cities. Calculation model and possible measures for mitigation and compensation of impacts.

Wedge 1.2. Footprint

  

Panels

  

 Construction

1250.0

kWh/m2

 

12.012

m3/kWp

 Use

0.8

kWh/m2

 

0.472

m3/kWp

Battery sizing

  

 Construction

4.18E−03

kWh/kWh

 

2.31E−01

m3/kWh

 Use

4.00E−04

kWh/kWh

 

1.43E−02

m3/kWh

Annual production per kW peak

Local value

kWh/kWp

Solar radiation

Local value

kWh/m2

Plant power \(\Pi\)

Available area/5.5

kWp

Annual production \(\Sigma\)

3,217,909.09

kWh

Gross cost of the plant

  

 Materials

1500 \(\Pi\)

 

 Supports

220 \(\Pi\)

 

 Inverter

350 \(\Pi\)

 

 Battery

200 \(\Sigma\)/365

 

 Design

7.50%

Net cost

 Works supervision, testing assistance

5.00%

Net cost

 Testing

2.20%

Net cost

 Safety charges not included in unit costs

3.50%

Net cost

 Surveys, assessments, and investigations

2.00%

Net cost

 Connection to the grid

5.00%

Net cost

 Unforeseen costs

5.00%

Net cost

Average service life

25

Years

  1. IEA, Best Practices Handbook for the Collection and Use of Solar Resource Data for Solar Energy Applications: Third Edition, https://iea-pvps.org/key-topics/best-practices-handbook-for-the-collection-and-use-of-solar-resource-data-for-solar-energy-applications-third-edition/