Table 19 Medium scenario: Wedge 1.2 detailed calculations—1

From: From the “Green Station” to the “Blue Station”: the role of the renovation of railway stations in the ecological transition of cities. Calculation model and possible measures for mitigation and compensation of impacts.

On-site production with solar panels

 

1. Footprint

  

 Panels

  

  Construction

1250.0

kWh/m2

 

12.012

m3/kWp

  Use

0.8

kWh/m2

 

0.472

m3/kWp

 Battery

  

  Construction

4.18E−03

kWh/kWh

 

2.31E−01

m3/kWh

  Use

4.00E−04

kWh/kWh

 

1.43E−02

m3/kWh

2. Available area

15,000.00

m2

3. Annual production per kW peak

1242.00

kWh/kWp

4. Solar radiation

1687.00

kWh/m2

5. Plant power

2727.27

kWp

6. Annual production

3,217,909.09

kWh

Gross cost of the plant

9,646,118

Eur

Materials

4,090,909

 

Supports

600,000

 

Inverter

954,545

 

Battery

1,763,238

 

Design

555,652

7.50%

Works supervision, testing assistance

370,435

5,00%

Testing

162,991

2.20%

Safety charges not included in unit costs

259,304

3.50%

Surveys, assessments and investigations

148,174

2.00%

Connection to the grid

370,435

5.00%

Unforeseen costs

370,435

5.00%

 Average service life

25

years

 Footprint/year

  
 

761,911.65

kWh

 

2379.00

m3