Table 21 Medium scenario: Wedge 2 detailed calculations

From: From the “Green Station” to the “Blue Station”: the role of the renovation of railway stations in the ecological transition of cities. Calculation model and possible measures for mitigation and compensation of impacts.

Rainwater collection and partial gray water recovery

Hydraulic plant sizing

  

 Construction

337.50

kWh/m3

4.20E−01

m3/m3

 Use

2.78

kWh/m3

1.18E−04

m3/m3

Accumulation capacity

500.00

m3

Gross cost of the plant

40,000.00

Eur

Average service life

15

years

Footprint/year

  
 

87,976.65

kWh

 

14.01

m3

Net production

  
 

− 87,976.65

kWh

 

155,139.01

m3

Wedge effect on the balance

  
 

100.12%

Energy

 

58.2%

Water

 

89.4%

Total