Table 4 Wedge 3—subsoil heat extraction with a low-enthalpy geothermal system: assumptions.

From: From the “Green Station” to the “Blue Station”: the role of the renovation of railway stations in the ecological transition of cities. Calculation model and possible measures for mitigation and compensation of impacts.

Wedge 3. Footprint

  

Probes sizing

  

 Construction

2,320

kWh/m

 

24.378

m3/m

 Use

1.747

kWh/m

 

0.472

m3/m

Storage tank/boiler

  

 Construction

4.18E−03

kWh/m3

 

1.27E−01

m3/m3

 Use

4.00E−04

kWh/m3

 

7.87E−03

m3/m3

Thermal needs

10.00

kW/m2

Geothermal power

0.05

kW/m2

Drilling depth

120.00

m

Number of 4-pipe probes

1

Probe/250 m2

Storage tank/boiler

2.50

l/m2

Gross cost of the system

  

Drilling

90.00

Eur/m probes

 Installation and cementation of the probes

30.00

Eur/m probes

 Heat pump

45.00

Eur/ m2

 Storage tank/boiler

0.35

Eur/l

 Design

7.50%

Net cost

 Works supervision, testing assistance

5.00%

Net cost

 Testing

2.20%

Net cost

 Safety charges not included in unit costs

3.50%

Net cost

 Surveys, assessments, and investigations

2.00%

Net cost

 Connection to the grid

5.00%

Net cost

 Unforeseen costs

5.00%

Net cost

Average service life

25

Years